Hood River Middle Fork Bridge

2006 was especially harsh on the North East side of Mount Hood damaging several parts of HWY 35 and washing out this bridge which MJ Hughes was hired by Anderson Enviromental to replace. The four abutments set on pipe piles which were drilled in very difficult cobble and boulder conditions. Access to place the girders was another challenge overcome by our team. 

Project Team and Stats:

Location: Parkdale, Oregon
Cost: Undisclosed
Start Date: July 2010
Completion Date: March 2011
Owner: Federal Highway
Engineer: OBEC Consulting Engineers
MJ Hughes Project Manager: Tim Whiteis
MJ Hughes Superintendent: Victor Vazquez
Subcontractors: Axis Crane, Hood River Sand and Gravel, TBH Drilling

   
   