A two span bulb tee bridge founded upon driven piles at bents 1 and 3 and drilled shaft foundation at bent 2. MJ Hughes self performed the drilled shaft on this project with rented Watson drill.
Project Team and Stats:
Location: Ruch, Oregon
Cost: 1,515,438
Start Date: March 2006
Completion Date: May 2007
Owner: Oregon Department of Transportation
Engineer: OBEC Consulting Engineers
MJ Hughes Project Manager: Ron Helmken
MJ Hughes Superintendent: Victor Vazquez
Subcontractors: |