Nestucca River Culvert Replacement

Located at the headwaters of the Nestucca River one of the Oregon Coasts premier fishing rivers dewatering and environmental concerns were the highest on MJ Hughes and Bureau of Land Managements radar. For this project we were allowed to pump the waters around us using twin 8″ diesel trash pumps with fish exclusion screens in place. Then we dug up and removed the failing 12′ diameter steel culvert, installed rip rap on the slopes, fish logs and a new bridge.

Project Team and Stats:

Location: Carlton, Oregon
Cost: 157,860
Start Date: July 2005
Completion Date: October 2005
Owner: Bureau of Land Management
Engineer: Bureau of Land Management
MJ Hughes Project Manager: Michael Hughes
MJ Hughes Superintendent: Victor Vazquez
Subcontractors: Axis Crane