Project Team and Stats:
MJ Hughes successfully overcame several obstacles in the completion of this contract with Oregon Department of Transportation. These challenges included working in prime salmonoid bearing watershed, 24-7 traffic control, narrow and steep work access and shoring the open roadway while excavating and constructing the bridge in stages. In the end MJ Hughes successfully removed the 12′ diameter existing culvert and installed a new bridge in it’s place.
Location: Grande Ronde, Oregon
Cost: 1,817,293
Start Date: March 2007
Completion Date: November 2007
Owner: Oregon Department of Transportation
Engineer: Oregon Department of Transportation
MJ Hughes Project Manager: Ron Helmken
MJ Hughes Superintendent: Jeff Ford
Subcontractors: |