State Route 2 Bridge Rehabilitation

This project repaired approximately 1/2 mile of SR 2. The scope involved removing spalled concrete, abrasive blasting, rebar repairs, watertight formwork, pressure grouting voids / repair areas, applying carbon fiber reinforcement and the application of pigmented sealer. Most of the work was constructed at night to minimize disruption to the approximately 250,000 vehicles per day.

 

 

Project Team and Stats:

Location: Everett, Washington
Cost: 4,168,313
Start Date: April 2011
Completion Date: September 2011
Owner: Washington State Department of Transportation
Engineer: Washington State Department of Transportation
MJ Hughes Project Manager: Scott Andrews
MJ Hughes Superintendent: Scott Russell
Subcontractors: Watershed Enviromental, The Traffic Control Company, Safway Scaffold, Carbon Fiber Wrap Co., Long Painting

 

 

 

 